Description
LOT A3: PREPARATORY WORK
Work dates: 2014-2015; 213 days
Work done:
Diversion of the Diddelengerbach, with two DN 2,500 pipes bored under the A13 motorway and two others under the railway line
Diversion of the STEP (wastewater), EP (rainwater), SES (drinking water), Créos (gas) and P&T (telecommunications) networks
Expansion of entrance to CFL’s Bettembourg marshalling yard
Construction of a Mabey-style temporary bridge 850 m retaining wall
Shifting of railway lines and digging of underground tunnel in Bettembourg marshalling yard (work done in 60 continuous hours over one weekend):
• Digging of a 16 m underground tunnel below the railway line
• Length of the track shifted: 750 m and a level crossing
• Replacement of the drainage
• Demolition of the old overhead line masts
• Construction of overhead line foundations
LOT B: EARTHWORKS AND DRAINAGE
Work dates: 2014-2015; 249 days
Key figures:
Earthworks: 800,000 m3
Embankment from excavated material: 400,000 m3
Excavated material to clear: 400,000 m3
Blending material: 500,000 t
DN 1,200 reinforced pipe for drainage: 12,000 m
300 manholes
DN 150 drain: 13,000 m
Lot C: CRANE FOUNDATIONS, MODALOHR, LIGHTING AND BUILDINGS
Work dates: 2015-2016; 209 days
Key figures:
1,200 DN 90 piles, average length 13 m, totalling 15,600 m
880 micropiles, average length 13 m, totalling 11,400 m
5,800 m3 concrete for Modalohr platforms (1,100 t of rebars)
2,400 m3 concrete for the gantry crane (340 t of rebars)
LOT D1: RGS (ROADWAYS/GRIDS/SUNDRY) WORK
Key figures:
Paving blocks: 16,000 m2
Crack channels: 18,800 m
DN 125 PE sheaths: 130,000 m
Compressed air hoses: 3,000 m
Fire hoses: 1,200 m
Asphalt concrete: 55,000 t
Porous asphalt: 19,700 m2
Stone mastic asphalt: 21,900 t
The work involved building a ladder of lines for trains to access the new rail/road intermodal terminals:
1,400 m of railways built for the Modalohr platforms 4 x 750 m of running track (combined transport)
Ladder of lines for connections, made up of 6 level crossings