Shell construction of Robert Schumann hospital is complete

Félix Giorgetti is expanding its operations internationally in a bid to increase its geographical footprint.

In 2010, under the leadership of Philippe Metzler and in association with CDC and Costantini, we won the contract to build the shell of the Robert Schuman hospital in Metz, France, and duly started work.

Between 10 and 20 people from our company have worked on this project since April 2010. As planned in the initial schedule, teams finished their work in May 2011, with just one team of five people remaining on site until the end of June 2011 to finish off the construction.

The works supervisor for Félix Giorgetti was Olivier Bolmont.

 