Secondary access on the south side of Belval West à BELVAL - WEST

Secondary access on the south side of Belval West à BELVAL - WEST

Description

A link road from south of the railway line to the Belval West site, avoiding the motorway.

This development essentially involved tunnelling underneath the railway line.

The work was carried out in two sections: From the northern side using Autofoncage (tunnel jacking) under the nine CFL cargo lines, and from the southern side using Autoripage (bridge sliding) creating an open-air tunnel.

Both sections were then separated to make a gap.

 

Construction period
2009-2011
Locality
Belval-West/Esch-sur-Alzette
Facts & Figures

Total length: approx. 100m

 

Contact us :

 + 352 49 88 88