News

The future Cloche d'Or exchange hub is taking shape

4 October 2022
Luxembourg - Cloche d'Or

Category

Public

The future Cloche d'Or exchange hub is taking shape

Started in November 2020, the structural works of the P+R Cloche d'Or are continuing. As planned, the elevations are finished, as well as the floors on the first half of the schedule.

Thanks to the drawer construction method (which consists of progressing the site at different stages in order to optimize resources), the finishes can begin on part of the P+R. The teams will carry out the containment of the first half of the building using a plastic film on the facades and set up a temporary central air boiler room. This will ensure sufficient heat and humidity to achieve the finishes. At the same time, the painting of the metal frame and the concrete pre-slabs will start, followed by the epoxy resin work on the floors. Downspout and masonry work continues.