OA 900 Boulevard Kockelscheuer
Category
Construction of a 140m long and 27m wide bridge over the A6 motorway.
Connection of Boulevard Raiffeisen and route de Kockelscheuer by a 140 m long mixed structure bridge.
The OA 900 has 2x2 lanes dedicated to road traffic, 2 tram lanes, footpaths and bike paths. It connects the new district of Ban de Gasperich with the roads coming from Leudelange and Bettembourg.
The structure consists of 2 concrete abutments and 3 piles supporting a mixed structure with a total length of 135m and a width of 27.30m.
27m
Width
140m
Length
800t
Steelwork
750t
Reinforcement
4-section structure
The structure has been installed in 4 sections. The motorway had to be closed to allow Kamag transport the first 3 sections. The 4th section will be constructed on site.
Each section weighs close to 400t, made up of the steel frame (200t), precast slabs and other components (200t).
The welding work was carried out after the sections have been installed, followed by reinforcement of the deck before concreting. The work was carried out in several stages and included night work.
Our client
Administration des Ponts et Chaussées
Key Figures
Minimum clearance height
5.23m
Max. longitudinal slope
6%
Constant cross slope
2.5%
Radius in plan
449.75m
Radius in length
1.000m
Concrete
3.400m3
Projets similaires
Hosingen cut-and-cover tunnel
2023
The cut-and-cover tunnel is the first section of the Hosingen bypass.
Dippach-Gare bypass
2023
Construction of a 2.2 km bypass to relieve traffic congestion on the rue des Trois Cantons.
Redesign of the Pontpierre interchange
2023
Redevelopment of the Pontpierre interchange on the A4 to improve traffic flow and safety for local residents.
Glaasbuurgronn and Groussheck viaducts
1998
As part of the construction of the Route du Nord, Félix Giorgetti carried out numerous works including the construction of two viaducts, Glaasbuurgronn and Groussheck.